Charlotte Water opened the Stowe plant on the Catawba River on Nov. 19, its first new wastewater treatment plant in 47 years.
The project costs about $650 million, paid for with revenue bonds, debt the utility repays from its own income. Charlotte Water says on its project site that its customers will not see rate increases because of the construction.
The plant is built to treat wastewater from northwest Mecklenburg County closer to where it is produced. That wastewater had traveled about 27 miles underground to the McAlpine Creek plant in Pineville, Charlotte Water Director Angela Charles said at the ceremony.
"It has been 47 years since our organization has commissioned a wastewater treatment facility," Charles said.
Stowe is shared with Mount Holly and Belmont, two Gaston County cities. Mount Holly was connected first, and its wastewater is already being treated, Charles said. The city has shut down its old plant.
Belmont's connection comes later. The city's new pump station and pipelines are expected to be built from 2026 to 2029, and once the station is running, Belmont is to begin shutting down its plant. The project's first phase is scheduled to be finished in 2028.
The plant can treat up to 15 million gallons a day and could later be expanded to 25 million. The state Department of Environmental Quality put nearly $34 million into the project over the last eight years, the department's secretary said at the ceremony.
The first conversations about the plant came in the late 1980s, Charles said, and the project has gone through four Charlotte Water directors.
The plant is named for Joseph C. Stowe Jr., a former director of the Charlotte-Mecklenburg Utility Department. His son Jay Stowe said his father kept the plant's drawings at home and showed them to almost any visitor.
"He was genuinely excited about this project," Jay Stowe said. His father would have had three thoughts about the plant, he said. The third "would have been, it cost what?"