The Study Charlotte Wanted on I-77 Takes Five Months. Its Deadline Is in Eight Weeks.

Charlotte has until October 5 to reverse itself on the I-77 South toll lanes or absorb a penalty the legislature wrote in July: a state bill the city attorney puts at $64 million, a freeze on its street maintenance money, and a block on every new state road project inside the city limits. Council members said they could not decide without an independent review. Staff told them Monday that one cannot be finished in time.

JB
Jack Beckett· Staff Writer
||7 min read
An illustrated news graphic shows an October 5 deadline for Charlotte to decide on I-77 South toll lanes, with clocks, a calendar, a highway map and a $64 million penalty folder.
An illustrated news graphic shows an October 5 deadline for Charlotte to decide on I-77 South toll lanes, with clocks, a calendar, a highway map and a $64 million penalty folder.

Charlotte has until October 5 to reverse itself on the I-77 South toll lanes or absorb a penalty the General Assembly wrote into the state budget in July: a bill the city attorney put at $64 million, a freeze on the city's annual street maintenance money, and a block on every new state transportation project inside the city limits until the bill is paid.

Council members have said for weeks that they could not make that decision without an independent review of the project. On Monday, August 3, city staff told a council committee that no such review can be finished in time.

Deputy City Manager Rebecca Hefner told the Transportation, Planning and Development Committee that the pool of consultants available for the work is small, and that the firms the city scoped it with said the time now available would yield "very limited information." A full review, one that compared the alternatives side by side, audited the data behind the original recommendation, validated its assumptions and added alternatives council members have asked about, would take three to five months.

Doing nothing is not neutral. The choice is whether to reinstate support for a roughly $3.2 billion, eleven-mile toll-lane expansion running south from uptown toward the South Carolina line, built under a 2024 public-private partnership, or hold the line and take the penalty. The Charlotte Regional Transportation Planning Organization, the regional board that decides which projects enter the state's construction pipeline, voted in May to withdraw its support, stalling the project and putting some $700 million in committed state money at risk of going elsewhere in North Carolina. Charlotte holds 31 of that board's weighted votes, more than 40 percent of the total and more than any other member, so what Charlotte decides largely decides the question.

The committee took no vote. Ed Driggs, the District 7 council member who chairs it, said the decision belongs to the full council and asked that it be taken up as soon as next Monday.

Two clocks, one of them invisible

City Attorney Andrea Leslie-Fite walked the committee through the provision, which began as a repayment bill in June before being folded into the budget. It contains two separate countdowns, and they work differently.

The first is fixed and Charlotte can act on it. The regional board has scheduled a September 23 vote on reconsidering, and any jurisdiction that reinstates its support of the board's October 16, 2024 resolution by October 5 escapes the penalty. Hefner told the committee the last regularly scheduled council meeting before the board votes is September 14. The council also meets August 10 and August 24, and the regional board itself meets August 19, when Charlotte has been expected to say where it stands. Council Member Reneé Johnson asked for a special meeting on top of those.

The second countdown is the one Charlotte cannot see start. A separate 90-day period ends with the project being struck from the state construction pipeline altogether, and it does not begin when Charlotte does anything. It begins when the transportation department files a report on its costs with a joint legislative oversight committee, and the statute sets no deadline for that filing. The two are independent: however long the department waits, the October 5 window to avoid the penalty does not move.

Mayor Rob Harrington, who took office July 1, asked Leslie-Fite to lay out that second period so the record of the meeting would be clear on it. Her answer was that the state decides when it starts, and that until the department files, nothing is running.

Leslie-Fite put the department's claim at $64 million for design work dating back to 2018, and said the city has heard estimates as high as $80 million. Counsel for the transportation department told her the regional board chair's $64 million figure was a reasonable approximation, she said, but has not committed to a number, because costs are still accruing.

What the review was supposed to settle

Council Member Victoria Watlington set the bar for commissioning one.

"My goal is not to get as close as possible as to what's already been scoped," she said. "My goal is to get to the right answer that represents the community's needs."

Among the questions she wants answered: where I-77 South actually fails, whether additional capacity is needed along the whole corridor or only at the pinch points, and whether a household at the area median income can access the benefit of what the public would be buying. She also asked how the traffic modeling accounts for induced demand, the pattern in which new road capacity draws additional traffic that partly erases the time it was built to save.

The firms the city scoped the work with did establish one thing about the original 2024 analysis: every alternative from no-build through a hybrid option was evaluated in it in some capacity. Hefner said the city had also identified a firm not currently working for the transportation department, on the view that independence would be fundamental.

The case for moving now

Driggs, the only member of the committee who did not support withdrawing in May, argued that the money is perishable and the calendar is longer than it looks. The procurement timeline has already stretched because the transportation department stopped working on the project, he said, and the request for proposals would not be finalized until roughly September or October of next year, meaning a reinstated project would not go to market for more than a year.

"There are a lot of people in the legislature that would love to get their hands on that $700 million," he said. "So yes, we can prolong the process, but just be aware that the $700 million that is currently committed will not necessarily be available at a later date."

Malcolm Graham, the District 2 council member who chairs the budget committee, said the road need and the objection to how it would be built are not in conflict.

"I clearly understand two things can be true," Graham said. "One, that I-77 needs to be widened, that there are pain points, that this is for future generations of Charlotte teens, but it shouldn't be done at the expense of black and brown communities. And so it has to be done together. There has to be trust and confidence in what we're doing."

A dispute over what the state has already paid

The sharpest exchange of the night was over a different set of numbers, and it ended unresolved.

Council Member LaWana Mayfield read a year-by-year account of Powell Bill payments to Charlotte, the state's annual street maintenance transfer to municipalities and one of the funds the penalty would freeze. They ran about $5.5 million in 2018, she said, $5.7 million in 2019, $5.7 million in 2020, $5.9 million in 2021 and $22.5 million in 2022. Since 2022, she said, the city has received nothing.

"So I have clear concerns that we are being challenged with a funding demand that is not aligned with what has come down to our city and tax dollars," Mayfield said, "especially from individuals that haven't passed the state budget on their own in a number of years."

Staff could not confirm the account in the room. Asked for the recent total, Hefner gave a figure of $13.6 million over the last several years, which does not reconcile on its face with the year-by-year account Mayfield had just read, and said she would get the date of the last disbursement from the budget office. Mayfield asked staff to come back with what the city should have received for the intervening years, with interest, noting that the allocation is largely population-based and that Charlotte is now the 14th largest city in the country.

Neither account was reconciled before the meeting ended, and no date was set for the answer. The Mercury has not independently verified either figure.

What the committee asked for instead

Nothing was decided. Graham asked staff for a line-item accounting of the $64 million, an identified source for the money if the city has to pay it, and a legal opinion on whether the statute itself is lawful.

"We need an accounting of the $64 million," he said. "And if the city were to pay it back, we need to be somewhat proactive in identifying the resources where those dollars will be coming from."

Johnson asked for an itemized cost breakdown covering the period since the 2024 approval, a report on how heavily the existing I-77 North toll lanes are used, and an explanation of how Gaston County is expanding I-85 without toll lanes.

"This meeting is simply because we're being penalized for representing the people," Johnson said.

Leslie-Fite reported she had already advised council by email that the sales tax revenue the state authorized for transportation could not be used to cover the repayment. Council Member Dimple Ajmera asked whether the mayor had raised the matter with Gov. Josh Stein. Harrington said he had not, and that what the city has is the letter the state transportation secretary sent community stakeholders on July 28, which affirmed the project's commitments and put the department's own figure for additional community investment at up to $300 million.

Mayfield objected to the framing.

"That up to $300 million is also very concerning," she said, comparing it to a sale price advertised as up to 40 percent off that turns out to be 5.

What the council does not have is the thing it said it needed. It has a claim it disputes, a number staff could not confirm, and a review that cannot be finished inside the window it has to decide.